Price an expedite from the work it changes Measure the change to the existing plan Start with a feasible standard schedule and identify what must change to meet the requested date. Overtime cost depends on what the base quote already pays: if normal wages are covered, enter the incremental premium and burden; if an entirely extra shift is needed, use its full added cost. A schedule-bump cost needs a documented basis, such as a real recovery expense on another order. Do not charge the same lost capacity both as full overtime and as displaced contribution without reviewing the overlap. Get the buyer to approve a defined offer Example wording: At your request, we can target [date] instead of the standard [date] for [part/revision/quantity]. Additional expedite charge is [fee], covering [specific changes]. This offer requires written approval by [cutoff], complete approved files and confirmation from [outside processor]. The original scope and price otherwise remain as stated in quote [number]. Please confirm the revised schedule and fee before we release the changed routing. Do not describe an unconfirmed processor slot as a guaranteed ship date. Write the fallback and record the result State what happens if approval arrives late or the buyer changes the drawing: the shop must review the revised delivery commitment again. Keep expedite approval with the traveler and note any outside-vendor confirmation. After shipment, compare actual overtime and freight against the fee so the next urgent job uses evidence rather than an arbitrary multiplier. This policy does not create capacity where none exists. If material, tooling, inspection or cure time makes the date infeasible, decline the date and offer the earliest schedule you can support.