Who pays when a part is scrapped because of a customer drawing error?

Your part priced in about 90 seconds, no account.

Stop the affected work, preserve the released requirements and agree on disposition before billing extra. A customer drawing error does not automatically establish who owes what; the accepted scope, your conformity, prior clarifications and contract matter. In the illustrative 20-bracket case below, scrapping the batch exposes $1,280 of incurred cost, while an approved rework route costs another $240. Present those alternatives with evidence rather than sending an unsupported scrap invoice.

See how QuotedPart connects to your workflow with its API, MCP server, autonomous quoting and shop-specific learning.

Example: the released hole is too small for the assembly

Assume 20 steel mounting brackets were made to an approved drawing with 0.250-inch holes. The customer's engineer now confirms the assembly needs 0.281-inch holes. Before the change, each part had $18 material, $30 machining and $10 outside finish, plus $120 of batch setup. Incurred batch cost is 20 × ($18 + $30 + $10) + $120 = $1,280. These are assumed shop costs, not a selling-price entitlement.

A proposed rework route uses $60 of batch setup, four minutes per part at a burdened $90 per hour, and one hour of final inspection at $60 per hour. Incremental rework cost is $60 + 20 × 4 / 60 × $90 + $60 = $240. This route assumes the customer explicitly accepts the resulting finish condition around the enlarged holes. If stripped or restored coating is required, obtain that supplier price and add it before seeking approval.

Illustrative cost exposure; neither figure is an automatically recoverable charge
Option or stageCalculationIncluded cost
Original batch incurred20 × ($18 + $30 + $10) + $120$1,280
Additional rework$60 + 80 min × $90/hour + $60$240
Total cost after accepted rework$1,280 + $240$1,520
Scrap and make an identical-cost new batch$1,280 + $1,280$2,560 before salvage

Separate three different causes

If the shop drilled a different size from the controlling drawing, start with a nonconformance and the shop's correction process. Do not describe your own programming error as a customer engineering change. If conforming parts need a new design, prepare a change quotation. If the original documents conflicted or the shop proceeded after noticing an unresolved error, preserve the correspondence and review responsibility before proposing a cost split.

No universal drawing-error rule resolves those facts. For example, Washington's commercial statute on express warranties says a goods description that becomes part of the bargain can create a warranty of conformity. That illustrates why the accepted description matters; it does not decide liability in another state or allocate every design risk. Get contract-specific legal advice when a material dispute remains.

Build a disposition package that someone can approve

Save the quote, accepted PO, drawing and model revisions, change messages, traveler, first-article results and affected lot identifiers. Record how many parts are untouched, partially machined, finished and already shipped. Quarantine affected pieces while the customer decides; do not blend them back into good stock or dispose of evidence needed for the investigation.

Show sunk cost separately from future spending. A replacement quote should identify recoverable material, salvage credit, canceled outside-service commitments and any original invoice adjustment. The example's $2,560 represents two batches of cost under a simplifying equal-cost assumption, not permission to bill the customer twice. Cost, proposed selling charge and contractual recovery are three different figures.

Agree on money, revision and release together

Example request: ‘Lot B-20 conforms to drawing revision C at the inspected hole size. Your proposed revision D requires larger holes. We estimate $240 additional rework cost under the attached routing, excluding coating restoration. Please approve the technical disposition and finish condition, and issue commercial authorization for the agreed rework price before we restart. Otherwise we will hold the identified lot pending instructions.’ Add the actual selling charge and schedule once your cost and markup are confirmed.

For future orders, propose a process requiring written approval of changes, disposition of existing work and adjustment of price and delivery before changed work starts. Have the accepted terms reviewed rather than relying on a broad sentence that the customer pays for every drawing error. The immediate next action is to document conformity and submit the least-wasteful technically acceptable option for approval.

Sources and limits

Claims are dated where they can change. Product calculations are examples from the stated inputs, not a promise about a customer's quote. Competitor wording is attributed to the source shown.

  • Washington RCW 62A.2-313 addresses express warranties, including conformity to a description made part of the bargain. It is cited as a state-specific example, not a nationwide liability rule. — source (checked 2026-10-30)
  • The quantities, costs and feasible rework route are hypothetical. Coating acceptance, salvage, responsibility and actual billing require separate approval or contract review.

Price one of your own parts

Drop a PDF drawing or a STEP file. QuotedPart reads the print, measures the model and prices it in seconds, on default shop rates you can change.

Your STEP file or PDF drawing

Free. No account, no email. Priced at our default US rates until you set yours.